During the construction of the elevated tunnel from the Okskaya street metro station to the Stakhanovskaya street station under construction the builders passed 105 meters of the main tunnel.

For the second month, after the installation of the first rings of reinforced concrete lining, the Herrenknecht-10690 (“Victoria”) tunneling complex on the section of the tunnel from the “Okskaya street” station has passed:

in December 2017: 51 meters running, 25 railway rings were installed;
in January 2018: with 50 p. m. planned for January, as of January 22, 2018, 54 running meters were passed, 30 railway rings were installed.
Thus, the tunnel to the station “Stakhanovskaya street” is carried out ahead of schedule.

The length of the distillation tunnels will be:

  • on the section “Okskaya street” – “Stakhanovskaya street” – 1993 m;
  • alembic tunnel on the section “Stakhanovskaya street – “Nizhegorodskaya street” – 1343 m.

Completion is scheduled for July 2018.