“The facility is 30% ready. Work is on schedule”,VasilyOrlov held a meeting on construction of the bridge across the Zeya River

Picture Stories

Construction of a temporary bypass road is nearing completion

Eduard Davydov, the project supervisor and the head of the USK MOST JSC branch office, reported on the work done.

On the right bank: “We have approached to the works in the riverbed, we expect toget directly to the riverbed in the third decade of June and start building pier No. 9. This is the deepest place of the river, in the middle of the fairway,” said Eduard Davydov.

Utility relocation works on the Gorky Street are also completed. Construction of a temporary bypass road is nearing completion. By the end of the month, it is planned to switch traffic and open a new construction site. Work on the construction of piers continues. “Approximately on June 20, we will begin the first stage of launching of theover-water superstructure. This is exactly the cable-stayed part of the bridge,” the project supervisor said.

He also noted that the supply of metal structures is proceeding as planned. There are enough of them to carry out work on the construction of the superstructure.

As for the left bank, work on construction of the piers is also underway. At the end of June, another stage of the launching of the superstructure is planned.

In total, the facility employs almost a thousand people and 163 pieces of equipment.

“The facility is 30% ready. The work is on schedule, it is going on as planned, despite another wave of flood,” Eduard Davydov said.

Source: Government of the Amur Region