Picture Stories
“Sabetta”: all works are completed!
010
USK MOST JSC has completed all the planned works within the framework of construction of the facilities
The SK MOST Group of Companies
Picture Stories
Dredging in the port of Sabetta is scheduled to be completed by the end of 2017
05
The amount of work planned for 2017 will be completed.
The SK MOST Group of Companies
Picture Stories
Dredging operations at the Sabetta seaport have been completed
04
Dredging works planned for 2016 in the seaport of Sabetta and on the sea channel of the Ob Bay have been
The SK MOST Group of Companies
Picture Stories
The port of Sabetta has completed dredging operations in the framework of navigation in 2015
07
JSC USK MOST completed dredging operations in the port of Sabetta as part of the navigation of 2015.
The SK MOST Group of Companies
Picture Stories
Nineteen Vessels Headed from the Port of Murmansk to the Port of Sabetta to Conduct Dredging
03
A large convoy of vessels led by the flagship, a self-propelled dredger “D’Artagnan,”
The SK MOST Group of Companies
Picture Stories
Preparatory Work Completed in the Arctic port of Sabetta
09
USK MOST Company has completed the preparatory work in the Arctic port of Sabetta under construction.
The SK MOST Group of Companies
Picture Stories
Dredging in the Port of Sabetta Done by Half by Early September
08
The dredging operations in the port of Sabetta began with the opening of the summer navigation season.
The SK MOST Group of Companies
Picture Stories
Nineteen Vessels will be Part of the Dredging Operations on Sabetta Arctic Port Construction Project
07
Nineteen vessels will be part of the dredging operation on Sabetta arctic port construction project on
The SK MOST Group of Companies